Main Facts:

Investor: STOEN S.A.

Performed works: locating the transformer station, laying the cables in the existing network, relocating the cable line, dismantling the overhead line
Implementation time: November 2001-December 2001

Implementation description:

An investment implemented for STOEN S.A. (currently Innogy S.A.), Mokotów-Ochota region, consisting in the construction of 15/0,4kV transformer station at Finałowa Street in Warsaw and connecting it to the existing 15kV medium voltage and low voltage network. Power engineering works included equipping the transformer station, relocating the cables, dismantling a redundant overhead line and connecting the new station to the existing network.

Zamknij