Main Facts

Investor: Pomiechówek Commune

Performed works: earthworks, foundations, a steel structure with roof covering, floors, ironwork, sanitary and electric installations, a multi-functional outdoor field, hall equipment, land development
Implementation time: June 2017-November 2017

Implementation description:

The investment implemented in collaboration with P.U.H PSB Paweł Święcki consisting in the construction of the sports hall with a connector to the existing building of the primary school and a multi-functional group of outdoor fields in Orzechowo Stare. The scope of the agreement included, among other things, the performance of foundations and a steel structure with a roof, the performance of indoor sanitary and electric installations, floors and indoor hall equipment. PSB and GIGA connected the hall with the existing building, carried out the necessary works consisting in hardening the land and laying sand and aggregate layers for outdoor fields. Despite the considerably short deadlines, both companies were able to complete all the works within 5 months.

Zamknij